Ripon Cathedral:
| |
|
Client: |
|
The
Chapter of Ripon Cathedral |
|
| |
|
Architect: |
|
Caroe
& Partners |
|
| |
|
Structural
Engineer: |
|
Hill
Cannon Consulting Engineer |
|
| |
|
Quantity
Surveyor: |
|
Sawyer
& Fisher |
|
| |
|
Contract
Period: |
|
24
weeks |
|
This project involved replacing the existing lead
coverings with new to the Central Tower of the cathedral and the
bellcote, situated on top of the Central Tower. To access the
Tower it was necessary to build a complicated scaffolding system
that took several weeks to erect.
The initial work included stripping off existing
lead coverings and carrying out any necessary timber repairs before
a new lead covering was fitted. The lead work was carried out
using traditional methods in line with the Lead Association’s
parameters. See Awards.


|